Skip to main content

Exit WCAG Theme

Switch to Non-ADA Website

Accessibility Options

Select Text Sizes

Select Text Color

Website Accessibility Information Close Options
Close Menu
Sweeney Law, PA Fort Lauderdale Business Lawyer
  • Exceptional Service
  • ~
  • Results Driven

Delay Claims In Construction Projects

ConstructionSite

Let’s assume that you complete a construction project, and the project itself is flawless, and exactly up to specifications (or, is exactly in accordance with the terms of the construction contract). Can you still be sued for breach of contract? In fact you can, if the project took longer than it was supposed to.

Who Brings Construction Claims?

A construction delay claim can be brought by the owner, but also may be brought by the contractor, in alleging that the owner of the property did something that kept the contractor from completing the job in a timely manner, thus costing the contractor additional money which ate away at the contractor’s profits.

Causes of Delay

A lot of things can cause a delay claim. In some cases the construction contract will specify what claims are excusable and which are not, or will have other provisions to try to ensure that delay doesn’t happen or that when it does, the delay is minimal.

However, things like the following can all lead to delay claims:

1)      The conditions of the site being different than what was anticipated

2)      Not being able to access a site

3)      Changes on zooming laws, or problems with governmental agencies granting necessary approvals

4)      Numerous changes or change orders

5)      Design plans that turn out to be impossible, not feasible, or just plain defective

Who is Liable for Delay, and When?

There are a number of factors that go into analyzing who is liable for delay claims.

Of course, cause is one major question—in some cases, the delay may not be the cause of either party. However, a party will be liable for conditions that it could have foreseen or avoided completely by a party.

For example, is a hurricane a sudden unknown cause of delay? Not necessarily in Florida—it’s more likely, an anticipated foreseeable event that the parties should have known about and built into their agreement. A contractor couldn’t allege a delay because he doesn’t have enough employees; the contractor needs to make sure he or she has the resources (workers) needed to do the job.

Sometimes, it may not be the contractor or the owner that is responsible, but a subcontractor that doesn’t do its job; construction projects often can’t move forward unless all steps are done in a predetermined order.

If the contractor truly could not foresee or avoid the delay, the delay may be considered an excusable delay.

Damages for Delay

Courts won’t give damages for delay, just for delay’s sake—a party needs to show actual damage from the delay. Sometimes this can be difficult to choose. A party has to show it lost money because of the delay. A contractor can show that he had to pay extra to lease equipment for longer, or that it lost out on other jobs, because this job took longer than anticipated.

Our Fort Lauderdale construction attorneys at Sweeney Law P.A. at 954 440-3993 can help you if you have a delay claim against an owner or contractor.

Sources:

corporate.findlaw.com/law-library/delay-claims-in-construction-cases-common-pitfalls.html

levelset.com/blog/construction-delay-claim-defenses/

Facebook Twitter LinkedIn

By submitting this form I acknowledge that form submissions via this website do not create an attorney-client relationship, and any information I send is not protected by attorney-client privilege.

Skip footer and go back to main navigation